SCA CLAIMS
scope of work
Change Orders
-
COVID-19 Impact Claims - Change Orders (click for list of required documents).
-
Review bulletin, sketch, Notice of Direction, Change In Contract, base contract drawings, etc. in concert with your supervisory personnel to establish additional costs or credit amount.
-
Generate the CO cover sheet and calculation sheet(s) on SCA approved forms.
-
Assemble the CO package complete with all requisite backup documentation.
-
Follow up with the SCA Change Order Unit in order to expedite their review and Fair and Reasonable Estimate (FRE) issuance.
-
Expedite a meeting with the reviewer.
-
Negotiate and settle the COs at the Change Order Unit.
Time Extension
-
Review project documentation (RFI's, Bulletins, NOD's, Meeting Minutes, Notices, Correspondence, etc) to establish a time extension narrative to be incorporated into the time extension schedule.
-
Review the time extension schedule generated by TMG or Client’s Scheduler.
-
Calculate the costs associated with the construction schedule deviation.
-
Meet with Joseph Topornycky's to obtain approval of time extension schedule.
-
Settle the number of compensable delay days with SCA scheduling unit.
-
Meet with Barbara McIntyre's to assess their FRE for time extension package.
-
Negotiate and settle the complete time extension costs.